Construction crews began work earlier this month shoring up the river banks on a portion of Stevens Creek that runs behind a Mountain View mobile home park. The project comes six months after three plots in the park were damaged by heavy rains, which caused a section of cliff abutting the creek to collapse. The sliding slope took the majority of three backyards with it, ripping away fences and back porches.

The crews will rebuild as much of the collapsed cliff walls as possible, according to Maria Ahmad, general manager of the Sahara Mobile Village. The aim is to get the three damaged lots back to the way they were before the landslide.

To impede erosion in the future, the crews are using a combination of concrete, rocks, wire and dirt to form a barrier against the movement of water through the creek and against rain. Dirt will also be packed in between the rocks, Ahmad said, which will allow plants and grasses to take root, further strengthening wall.

According to John Vidovich, head of the real estate firm that owns the Sahara Mobile Village, construction was delayed due to an abundance of bureaucratic red tape that he and his company, De Anza Properties, had to negotiate before breaking ground.

Before Vidovich could begin work, he needed to secure approval from eight local, state and federal agencies. "I learned what hell is, and it's working with these public agencies," he said.

What's local journalism worth to you?

Support Mountain View Online for as little as $5/month.

Learn more

The project was supposed to begin at the start of August. But it took months of meeting with officials from the city of Mountain View, the Army Corps of Engineers, the Department of Fish and Game, California Regional Water Quality Control Board, the Santa Clara Valley Water District, the National Marine Fisheries Service, Caltrans, and the state's Department of Housing and Community Development before all the appropriate signatures could be collected.

"It put us behind," Ahmad said, noting that she and Vidovich had hoped to begin construction by Aug. 1. Now construction crews have under a month to complete their work. Their permits only allow them to work through Oct. 15.

The project is going to cost De Anza Properties more than $1 million, but in the end, Ahmad said, "It's going to look nice and it's going to be pleasing for us. It's going to make things safer."

Stay informed

Get daily headlines sent straight to your inbox.

Sign up

Follow Mountain View Voice Online on Twitter @mvvoice, Facebook and on Instagram @mvvoice for breaking news, local events, photos, videos and more.

After delays, work begins on mobile home park

Repairs to landslide damage held up by regulations, red tape

by / Mountain View Voice

Uploaded: Fri, Sep 23, 2011, 11:38 am

Construction crews began work earlier this month shoring up the river banks on a portion of Stevens Creek that runs behind a Mountain View mobile home park. The project comes six months after three plots in the park were damaged by heavy rains, which caused a section of cliff abutting the creek to collapse. The sliding slope took the majority of three backyards with it, ripping away fences and back porches.

The crews will rebuild as much of the collapsed cliff walls as possible, according to Maria Ahmad, general manager of the Sahara Mobile Village. The aim is to get the three damaged lots back to the way they were before the landslide.

To impede erosion in the future, the crews are using a combination of concrete, rocks, wire and dirt to form a barrier against the movement of water through the creek and against rain. Dirt will also be packed in between the rocks, Ahmad said, which will allow plants and grasses to take root, further strengthening wall.

According to John Vidovich, head of the real estate firm that owns the Sahara Mobile Village, construction was delayed due to an abundance of bureaucratic red tape that he and his company, De Anza Properties, had to negotiate before breaking ground.

Before Vidovich could begin work, he needed to secure approval from eight local, state and federal agencies. "I learned what hell is, and it's working with these public agencies," he said.

The project was supposed to begin at the start of August. But it took months of meeting with officials from the city of Mountain View, the Army Corps of Engineers, the Department of Fish and Game, California Regional Water Quality Control Board, the Santa Clara Valley Water District, the National Marine Fisheries Service, Caltrans, and the state's Department of Housing and Community Development before all the appropriate signatures could be collected.

"It put us behind," Ahmad said, noting that she and Vidovich had hoped to begin construction by Aug. 1. Now construction crews have under a month to complete their work. Their permits only allow them to work through Oct. 15.

The project is going to cost De Anza Properties more than $1 million, but in the end, Ahmad said, "It's going to look nice and it's going to be pleasing for us. It's going to make things safer."

Comments

EB
Monta Loma
on Sep 23, 2011 at 3:08 pm
EB, Monta Loma
on Sep 23, 2011 at 3:08 pm
3 people like this

What? They didn't get National Highway Transportation Safety Administration approval? They're in big trouble now.


Mondy
another community
on Sep 23, 2011 at 3:33 pm
Mondy, another community
on Sep 23, 2011 at 3:33 pm
3 people like this

While I feel bad for the folks that were effected by the landslide I must say that I do not support the repairs that are planned.

Once again people and property are placed before the health of our creeks and the fish and wildlife that use these corridors.

If development had not been allowed so close to the creek this would not have happened. The right thing to do would be to move the park way back from the creek and give the creek back some of its floodplain.

The bank hardening planned will provide only a temporary solution because in the end the stream always wins. Flooding is a natural process which should be respected.